Description This project consists in delivering a full power CLIC Drive Beam klystron modulator for klystron tests purposes in Building 112. the delivery is foreseen in 2018. This project is organized in 2 sub-projects, the Pulse Transformer (PT) and the (primary side) Klystron Modulator (KM). 
| Management - Documentation (DFS folder / EDMS)
- Pulse Transformer
- Klystron Modulator
- Project Mandate KM
- Milestone plan KM
- Technical Spec. KM
- Functional Specification KM
- Follow-up
- Open actions
- Minutes of Meeting (MoM)
| Communication - Presentations
- Publications
- Conference / journals
- CDS
- Photos
|
Technical Development - Design report KM
- Manufacturing Folder KM
- Installation
- DIC ether
- Pre-DIC Power
- Integration/Rack layout
- Installation procedure
| Procurement | Tests & commissioning & operation - Reception tests
- Test Procedure
- Prototype converter tests
- On site tests
- Operational note / note d’opération
- EPC Database issues
|