Who |
objective (in order of priority for each person) |
Due Date |
Julien
|
- Harmonize power converter design for reg FGC3 control
- Re-utilise as much existing components in L4 current converter
- Obtain two identical converters (operational + spare which could be used in 3MeV)
- Converters operationals by end 2016.
|
end 2016
|
Julien
|
- Prepare project mandate, include clarifications on associated commercial power supplies (Tube grid, screen & bias), and exlude RF work due to interfaces modifications
- Obtain consensus un project mandate by end of Septembre 2015
|
Sep 2015
|
Julien
|
|
Oct 2016 |
Julien
|
- Prepare and circulate functional specification including the new interfaces with RF
- Issue the purchases of all components by end 2015
|
end 2015 |