MarXDisCap Open actions

Updated 26th January 2018

Who

objective (in order of priority for each person)

Due Date

Todor

  • Simulate active filter operation by insering it into SMH42 simulation
  • Check Optical Interface Module solution through consultations with CCE
  • Schematic update
  • Optimize active filter design through analytical calculation
  • Polary switch follow-up
  • Prototype test plan with Stéphane

1 Feb

1 Feb

1 Feb

1 Feb

1 Feb

29 Jan

Julien

  • Check GBF to control SMH16 active filter using selected modulator crate
  • Test StateControl card to start charging via charger's analog interface
  • Make sure SateControl card is programed and test all 5+4 outputs 
  • Check Optical Interface Module solution, consult CCE and Todor

1 Feb

1 Feb

1 Feb

1 Feb

Stéphane

  • Update full converter schematic
  • Propose differential voltage measurement circuit (Miguel Bastos to be involved for the design)
  • Draft global converter integration design 
  • Report status on MCPM and MCBM mounting
  • Prototype test plan with Todor

1 Feb

1 Feb

1 Feb

1 Feb

29 Jan

Davide

  • Send AD functional spec for pre-revision to AD and SLM

1 Feb